This particular question can be solved using the unitary method (this method include solving the problem for 1 unit and then multiplying it with how many units are required), which is proceded as :-
3 persons can rewire the house in = 4 days
1 person can rewire the house in = 3/4 days
Hence, 4 persons can rewire the house in = (3/4)×4 days
=3 days.
(Now writing the proper statement at the end to complete the answer)
So, if Jasminder uses 4 persons using 3 to rewire her house, it will take 3 days.
-