Activity Discussion Math Maths

  • Maths

    Posted by Anagha on June 5, 2023 at 3:54 pm

    Jasminder estimates that 3 persons could rewire her house in 4 days. If she uses 4 persons instead of three, how long should they take to complete the job?

    Isha replied 10 months, 2 weeks ago 2 Members · 1 Reply
  • 1 Reply
  • Isha

    Member
    June 6, 2023 at 12:06 pm
    Helpful
    Up
    0
    Down
    Not Helpful
    ::

    This particular question can be solved using the unitary method (this method include solving the problem for 1 unit and then multiplying it with how many units are required), which is proceded as :-

    3 persons can rewire the house in = 4 days

    1 person can rewire the house in = 3/4 days

    Hence, 4 persons can rewire the house in = (3/4)×4 days

    =3 days.

    (Now writing the proper statement at the end to complete the answer)

    So, if Jasminder uses 4 persons using 3 to rewire her house, it will take 3 days.

    • This reply was modified 10 months, 2 weeks ago by  Isha Talwaria.